Transportation & Environment Services

somersetphasesforweb

Somerset Street

On May 28 Phase Two of the project begins. Traffic information is available here.

This summer the City of Saint John and its contractors will begin work on the Somerset Street Reconstruction Project.  This project includes the installation of a new storm sewer, repairs to the existing sanitary sewer, and road reconstruction consisting of a new curb, sidewalk, and asphalt surface. 

Work will take place in three phases from Samuel Davis Drive to Wellesley Avenue.  Residents in the area may experience noise and dust, while motorists will experience significant traffic detours.

Motorists are encouraged to use Millidge Avenue as an alternate route, adjust travel times when possible, and consider alternate transportation
methods.

 Phase 1    2 months*
Samuel Davis Drive to Thornbrough Street
Begins April 8th, 2013
 Phase 2    1 month*

Intersection of Wellesley and Somerset Street
Begins May 28, 2013


Phase 3    2 months*
Wellesley Avenue to Thornbrough Street
*Duration times are approximate and subject to change.